Your rough timeline
Two things move the number more than anything else: whether you start from a plan or a blank page, and how large the house is. Pick both.
-
Pre-construction 30 to 45 days
-
Permitting 2 to 3 weeks
-
Construction 8 to 10 months
Starting from a planbook plan is the single largest thing you can do to shorten a build without cutting quality.
Get Your Lot EvaluatedWhat each stretch is for
Pre-construction
The phase that determines whether the rest of the job goes well. Everything decided here is cheap to change; everything decided later is not.
- Plan selection or custom design development
- Structural engineering and a soils report
- Septic design or utility coordination where needed
- Interior and exterior selections
- A fixed budget you can hold us to
Permitting
Mostly waiting, and mostly overlapping. We submit as soon as the drawings allow so this runs alongside the tail of pre-construction rather than after it.
- County or municipal building permit
- On-site sewage facility permit, on acreage
- HOA architectural committee review
- Shoreline permitting on waterfront lots
- Driveway and culvert approvals
Construction
The visible part. One superintendent stays on your job from clearing to keys, and you get a written progress report every week regardless of whether anything went wrong.
- Site work, foundation, and framing
- Roof, windows, and dry-in
- Mechanical, electrical, and plumbing rough-in
- Insulation, drywall, and interior finish
- Punch list and final walkthrough
What happens on site, in order
Construction is the part you can watch. The sequence rarely changes; only the pace does.
-
Month 1
Site work and foundation
Clearing, pad preparation, and forming. The engineered slab is poured and cured before anything sits on it. This is the most weather-sensitive stretch of the whole build.
-
Months 2–3
Framing
The house takes shape faster here than at any other point, which is why this phase feels encouraging and the next several feel slow. Framing inspection follows.
-
Month 3–4
Roof, windows, and dry-in
Sheathing, roofing, and window installation close the building envelope. Once the house is dried in, rain largely stops affecting the schedule.
-
Months 4–5
Rough-in
Plumbing, electrical, HVAC, and low-voltage go in the walls, followed by inspections. Nothing visible changes for weeks, and everything that matters is happening.
-
Month 5–6
Insulation and drywall
The envelope is sealed and the interior gets its surfaces. This is the point where the house stops being a frame and starts being rooms.
-
Months 6–8
Interior finish
Trim, cabinetry, tile, countertops, and paint. The longest stretch, and the one where selections made months ago either fit together or do not.
-
Months 8–10
Fixtures and exterior
Flooring, lighting, plumbing fixtures, appliances, driveway, and landscape. Multiple trades on site at once, sequenced tightly.
-
Final 3–4 weeks
Punch list and walkthrough
The slowest-feeling weeks of the build and the ones that determine how the house feels to live in. We walk it with you, list everything, and finish it before you move in.
About the schedule
If you’re looking for a builder that matches structural integrity with personal integrity, look no further. We didn’t just buy a house; we joined a community supported by people who clearly love what they do.