Chapter Eleven The Timeline

How long it actually takes

Most builders answer this with a number they hope you forget. These are the durations we work to, phase by phase, with the things that stretch them named honestly.

A schedule you can plan a life around.
Two Questions

Your rough timeline

Two things move the number more than anything else: whether you start from a plan or a blank page, and how large the house is. Pick both.

Where you are starting
Roughly how large
Contract to keys
10–12
Months, typical
  • Pre-construction 30 to 45 days
  • Permitting 2 to 3 weeks
  • Construction 8 to 10 months

Starting from a planbook plan is the single largest thing you can do to shorten a build without cutting quality.

Get Your Lot Evaluated
The Three Phases

What each stretch is for

I

Pre-construction

30–45 days planbook · 60–120 days custom

The phase that determines whether the rest of the job goes well. Everything decided here is cheap to change; everything decided later is not.

  • Plan selection or custom design development
  • Structural engineering and a soils report
  • Septic design or utility coordination where needed
  • Interior and exterior selections
  • A fixed budget you can hold us to
II

Permitting

2–3 weeks outside Harris County

Mostly waiting, and mostly overlapping. We submit as soon as the drawings allow so this runs alongside the tail of pre-construction rather than after it.

  • County or municipal building permit
  • On-site sewage facility permit, on acreage
  • HOA architectural committee review
  • Shoreline permitting on waterfront lots
  • Driveway and culvert approvals
III

Construction

8–10 months · 9–12 months at 4,500+ sq ft

The visible part. One superintendent stays on your job from clearing to keys, and you get a written progress report every week regardless of whether anything went wrong.

  • Site work, foundation, and framing
  • Roof, windows, and dry-in
  • Mechanical, electrical, and plumbing rough-in
  • Insulation, drywall, and interior finish
  • Punch list and final walkthrough
Month By Month

What happens on site, in order

Construction is the part you can watch. The sequence rarely changes; only the pace does.

  1. Month 1

    Site work and foundation

    Clearing, pad preparation, and forming. The engineered slab is poured and cured before anything sits on it. This is the most weather-sensitive stretch of the whole build.

  2. Months 2–3

    Framing

    The house takes shape faster here than at any other point, which is why this phase feels encouraging and the next several feel slow. Framing inspection follows.

  3. Month 3–4

    Roof, windows, and dry-in

    Sheathing, roofing, and window installation close the building envelope. Once the house is dried in, rain largely stops affecting the schedule.

  4. Months 4–5

    Rough-in

    Plumbing, electrical, HVAC, and low-voltage go in the walls, followed by inspections. Nothing visible changes for weeks, and everything that matters is happening.

  5. Month 5–6

    Insulation and drywall

    The envelope is sealed and the interior gets its surfaces. This is the point where the house stops being a frame and starts being rooms.

  6. Months 6–8

    Interior finish

    Trim, cabinetry, tile, countertops, and paint. The longest stretch, and the one where selections made months ago either fit together or do not.

  7. Months 8–10

    Fixtures and exterior

    Flooring, lighting, plumbing fixtures, appliances, driveway, and landscape. Multiple trades on site at once, sequenced tightly.

  8. Final 3–4 weeks

    Punch list and walkthrough

    The slowest-feeling weeks of the build and the ones that determine how the house feels to live in. We walk it with you, list everything, and finish it before you move in.

Being Straight With You

What adds time

Every one of these is survivable. All of them are cheaper to plan for than to discover.

  • Adds 2–6 weeks

    Late selections

    A house waits on decisions more often than on materials. We front-load selections in pre-construction for exactly this reason.

  • Adds 2–8 weeks

    Changes after framing

    Moving a wall on paper costs an eraser. Moving it after rough-in costs demolition, re-inspection, and everyone’s schedule.

  • Adds 3–8 weeks

    Septic and well on acreage

    Rural sites need an on-site sewage permit and often a well. Both have their own review timelines and neither can be rushed.

  • Adds 2–6 weeks

    HOA architectural review

    Gated communities review elevations, materials, and colors before permitting. Revisions add a round trip each time.

  • Adds 1–4 weeks

    Sustained wet weather

    Site work and foundation are the vulnerable phases. Once dried in, weather matters far less. We schedule toward dry-in for this reason.

  • Varies

    Long-lead specialty items

    Certain windows, appliances, and imported stone run months out. We identify those during selections and order them first.

Great room with exposed cedar beams and a stone fireplace, seen from the entry Twelve months earlier, this was a survey
Where It Ends Up

A year is a long time to trust someone

Which is why we report weekly in writing, keep one superintendent on your job from slab to keys, and put every change in writing before it happens. The schedule is only worth something if you can see it moving.

How we build →
Questions We Get

About the schedule

If you’re looking for a builder that matches structural integrity with personal integrity, look no further. We didn’t just buy a house; we joined a community supported by people who clearly love what they do.
Clarity M. · Google review
Read client reviews →

Ready to start the clock?

Send us the address or parcel ID. We will tell you what we see, what it will likely take, and roughly when you would be moving in.